Oct 27, 2018: Port Moller Rebuild Pictures!


Port Moller facility is coming together fast. What a great crew and effort by so many.

Periodically, we will post new photos of the rebuilding progession.
Latest photos at the bottom.

Post Fire Cleanup and before reconstruction starts

postfirecleanup.jpg

Barge arrives

Equipment.jpg

Pilings are going in really fast.

AerialPilings.jpg

The pilings are nearly all in place.

Pilings.jpg

pilings-may31.jpg

jun5-18.jpg

Late June 2018. The dock is nearly complete.

Rebuild-LateJune2018.jpg

Late July 2018. The Power House and Refrigeration building framing is rapidly taking shape.

powerhouse.jpg

August 7, 2018. The roof is going on the Power House and Refrigeration building.

partial_roof_aug7_2018.jpg

August 7, 2018. The cement floor is getting poured in the Power House and Refrigeration building.

cement_floor_aug7_2018.jpg

August 20, 2018. The final load of construction supplies arrived!

supplies-barge.jpg

September 5, 2018. Walls beams and trusses in place.

sept2018a.jpg

September 5, 2018. Walls beams and trusses in place.

sept2018b.jpg

September 25, 2018. Most all trusses in place and roof going on.

sept2018c.jpg

October 10, 2018. Roof and walls are up. Interior work, including concrete is well underway!

oct10.jpg

October 27, 2018. Exterior work completed. This is from a similar view angle as the Post Fire Cleanup picture at the top.

plantfromshore.jpg

October 27, 2018. Concrete floors complete. Interior construction is going as fast as possible.

interior.jpg